|
|---|
Expansion Photos - February 2012
Watch us grow! Friday, February 24 - In preparation for the addition of a sink in the Public Meeting Room, the floor was removed and a trench was dug. Plumbing for drainage was installed in the trench.
Electrical lines were run on the adult side as well.
Wednesday, February 15 - The framing on the teen side was completed and the roof was added.
Friday, Feburary 10 - The removal of the outside wall on the Adult side of the library was completed and all of the cinder blocks were removed. Also, over the last day or two the roof was added and iron workers continued their work on the metal structure.
Thursday, February 9 - Welding work was in full swing on the Adult side structure. Demolition of the outside wall also continued at a brisk pace.
Wednesday, February 8 - The temporary wall on the Adult side is completed, and demolition of the outside wall began immediately with the removal of the windows.
Tuesday, February 7 - The temporary wall at the back of the Adult side is almost completed, with layers of drywall, plywood and insulation. The last piece would be finalized as soon as the radiators could be removed.
Monday, February 6 - A lot of progress! A crane arrived early along with steel beams. By the end of the day the basic structure for the Adult expansion was in place.
Friday, February 3 - Removal of the stacks on the back wall of the Adult side was completed.
Thursday, Feburary 2 - Work continued on the removal of the soffit from the teen expansion site.
Wednesday, February 1 - There was further removal of the soffit on the adult side, revealing the bricks underneath.
|
|---|