Expansion Photos - February 2012
Watch us grow! Thursday, March 29 - Preparation for the roof continued on the adult side. The teen side was coming together more and more. Painting started inside the existing building. A new palate of colors gives the library a fresh look.
Tuesday, March 20 - Brick laying started on the adult side.
Tuesday, March 13 - The weather behaved amazingly for a day of pouring concrete. The trench in the public meeting room, the adult, and teen sides were all filled
Wednesday, March 7 - Both the Teen and Adult sides showed marked progress in the framing in preparation for drywall.
Thursday, March 1 - They began setting the framework for the walls on the Adult Side. The plumbing in the Public Meeting Room was completed as well.
|
|---|